Technip

Business description

 

   Construction field:

 

 Current:  Yamal LNG module construction  project in Qingdao yard , assigned with Shanghai Yamagaz (Technip from France ) Co. Ltd.

 Previous:

1. Express Rail Link contract-810A, West Kowloon Terminus Station Project  --ALFASI (Hong Kong) Construction Company

2. Eiffel Tower / Venetian restaurant building project from Alfasi in Macao

3. Koniambo nickel plant project in Hatch Company from Australia.

4. Offshore oil /gas platform construction in BP/Conocophilips and COOEC

5.  CSPC Nanhai Shell petrochemical plant project (JGC) in Huizhou of Guangdong

6. Firepower /hydro power plant  in Sino-hydro Bureau Eighth Co., Ltd. China

 7. Shipbuilding manufacturing at Guangzhou shipyard international Co. Ltd  

Education

 

Mechanical manufacture and process discipline graduated at Hunan University, Hunan in China; 1989-1993.

English: level VI

Professional Affiliations

Gained Professional Mechanical Engineer in 2000 year, approved by Mechanical industry institute  of China .

BP Du pong safety course training and license gained: STOP/ASA on 2002 year.

    Summary of Experience    

     

·24+ years’ construction work experience in oil, LNG, chemical, mining smelting industry.

      Excellent experience in design, material, schedule, safety & quality control.

· Good management experience in preparation of project start up procedure, construction procedure, project standards, effective mobilization plan of construction equipment, material & labor.

· Expert in steel structure, experience in fire & explosion proof, like fire retardant paint.

·  Fluent in English.

 

     Peter has excellent safety management experiences and  skills on firefighting and explosion proofing design/construction/operation,especially in the field of  oil/gas offshore platform /petro chemical plant construction/installation/ operation / maintainance and to  taken the safety responsibility for overall project peoples,like Building owners,end-user,architects,consultant engineers, control company,contractor/installers....etc, 

     Peter has good knowledge of related Chinese and international regulations(ATEX code)/certifications on building explosion proof and firefighting design /construction/installation/operation.

    Peter also has  gained excellent  coordination skills  on schedule/ quality/design/material control with project contractor/client /vendor / the third parties(like BV,DNV,CCS) .

    He is familiar with using and good understanding international codes/ standards such as  ASME, II, V, VIII, IX, B31.3, ASTM, AISC 360, API 686, API 1104, AWS D1.1, D1.5, D1.6, NACE 0103, DNV, GB, ISO 9001, JIS, etc and other relevant national codes/ standards in China.

     Good computer skills on project control of Microsoft  P6/Excel/Tekla Structures / Auto CAD/3D3S/ Autodesk Navisworks/Bentley Project wise Navigator/PIMS ....etc.

Specialties

Construction safety advise/production consultant at factory/vendor

Mechanical  manufacturing/installation supervision and Quality control management 

Steel structure /process piping fabrication supervision /inspection at supplier

HVAC dynamic &static equipment manufacturing and installation supervised

Project plan implement and HSE management

Project Mechanical Completion and Handover management

Relevant Experience

 

Jul. 2016~Present:

  Russia Yamal LNG project, FWP1E Stick built Fabrication group, at Qingdao McDermott  Wuchuan yard, China,as a structure construction /safety supervisor.

     Peter Zhou now is  in charge of  steel work fabrication supervision, including daily safety /progress/safety/quality activities; reviewing and approve material purchase orders /monthly production plan ; monitoring the fabrication&NDT&painting &packing and delivery schedule that prepared by  QMW sub-contractors for ensure compliance with project delivery requirement;

   In charge of  this project overall  construction safety management issue, included JSA/PTW review and approval for heavy lifting activities/working on the height ;hot work/confine space ;supervised the project daily tools box meeting/JSA/construction method/labor resource/material MSDS /certificates validation ; especially on confine space/equipment operation/fuel gas filling/coating/hot work/work on height/heavy lift and the areas when a flammable medium(gas/vapor/mists/dust,...etc) was present to a dangerous quantity. Used gas detection/fire and smoke detectors to check and reduce the fire accident/explosion hazard risk in time. Provided safety suggestion for fireproof/explosion explosion field on design /construction /operation /maintainance issues.

   Performed explosion hazard assessment/fire accident risk assessment on daily basis for the hot work.height work,confine space, heavy lift,...etc  and take action immediately to prevent and control of fires/explosions and other safety risk 

 Mar.2016~ July.2016

Russia Yamal LNG project, MWP-10a/b Modules at Qingdao CPOE site of Shandong, China, as a structure/HVAC and outfitting supervisor.

Assigned with Yamgaz management consultant (Shanghai)Co.ltd ----Branch Co. Ltd of Technip France  in China 

      Peter Zhou was in charge of MWP10a LNG module (AG&P060-PAU-001/02)construction supervision work at Qingdao CPOE yard,  

       His work scope was that:  daily monitoring and advised on construction safety issue,like fireproof  protection,height work , explosion proof equipment inspected and testing at construction site;  Supervised the project daily tools box meeting/JSA/construction method/labor resource/material MSDS /certificates validation ; especially on confine space/equipment operation/fuel gas filling/coating/hot work/work on height/heavy lift and the areas when a flammable medium(gas/vapor/mists/dust,...etc) was present to a dangerous quantity. Used gas detection/fire and smoke detectors to check and reduce the fire accident/explosion hazard risk in time.

    

     Provided design consultant and reasonable suggestions to improve construction/operation condition on safety/technical/schedule /cost/quality cases.

      Reviewed  and approval this project fireproofing/explosion proof plan /emergency escape plan/workshop safety allocation map/high accident hardzards area /operation area safety route map plan.   

       Supervised  steel structure workshop fabrication and site erection  work , included ventilation &exhaust duct system inside of HVAC room   ; architecture work supervision for HVAC room and stair tower ;punch list  /RFI /NCR /mechanical completion work field tracing and closed ;  vendor equipment /steel members' delivery schedule tracing and hand over management with CPOE  contractor/sub-contractor of Shandong Jian gong; daily pushed and traced site plan  on mechanical/structure construction activities with site repre. who come from Yamal client /Technip France Co. /JGC/BV ...etc .;

     Daily coordinated module construction issue, including site planning, process, fabricating plan, module pipeline, welding, scaffolding, and heat tracing, insulation work; daily monitored construction safety issue, such as ,JSA meeting before heavy lifting activities/working on the height ; PTW reviewed and approval for confine space work /hot work /working above water /hydro-test /RT test.....etc; daily coordinated with Yamgaz QA/QC department /design engineer on some urgent of key quality issues on site;  reviewing material submissions, method statements, Quality plan and various ITP; Leaded a team of  engineers, inspectors and work supervisors to ensure the quality of the works are achieved to the relevant standards and specification.  

 Express Rail Link contract-810A , West Kowloon Terminus Station  Project in HK, as a Steel Fabrication Supervisor at Shanghai Baoye Company & Dong wan Yin ji Factory and CMIIC supplier in Zhongshan city of Guangdong.

Assigned with Alfasi Construction (Hongkong) Ltd

 Oct. 2014 –Mar.2016

   Peter has worked  for Alfasi (Hong Kong) Co. Ltd., directly report to Alfasi fabrication manager. As a fabrication supervisor for Hongkong 810A WKT Express Rail Link Project , supervised the  steel structure fabrication/painting/packing and delivery works at four factories in China ,including Shanghai Baoye steel Co.ltd  (SBC)& Dongguan Yinji steel Co.ltd (YJ)& CMIIC at Zhongshan base(CHSIC) and Hua Yu Steel Co. at Jiangmen City (HY-JM) in Guangdong province.

   His major job responsibility in 810a Western Kowloon Terminal  Rail Station project at HY/CSHIC factory  was that:

   Coordinated and supervised the Span-A and Span-B/C roof truss fabrication /painting and delivery works,( included 9 sets of roof truss heavy steel /cladding and facade works, Architectural Builders Works & Finishes (ABWF) and E&M works of various contracts, supervised all of  fabrication quality activities in process /project progress/raw material incoming /IFC design drawing review/  steel production delivery plan monitoring at supplier in accordance with  MTR client requirement; Audit and review all related QA/QC documentations which submitted by supplier; cross checking the critical quality issue in supplier workshop like dimension control/welding NDE/I.D marking of raw materials /mill certification sheet/ shop drawing revised/site design change /RFI/NCR/Contract variation/Site instruction.....etc.; reviewing and approve all purchase orders /monthly production plan /delivery schedule that prepared by supplier and sub-contractors for ensure compliance with the contract requirement; manage the variations from supplier/sub-contractors; control and manage all QA responsibilities ;submit weekly QA/QC report/monthly production schedule report to Hong Kong head-office; reviewing and approve all the final QC dossiers from supplier.

Eiffel Tower&Link bridge (Venetian Parcel 3,Macao) project , as a Fabrication Supervisor at Modern Heavy Industry Steel supplier in Shanghai.

Assigned with Alfasi Construction (Hongkong) Ltd 

Nov. 2013 –  Sep. 2014

   Peter has worked for Alfasi (Hong Kong) Co. Ltd., at MHI factory (Modern Heavy Industries Co. Ltd) in Shanghai, directly report to Eiffel Tower project manager in Alfasi (Macao) office.

   The productions in this project at MHI supplier was including the whole Eiffel Tower steel fabrication work and the mechanical supports for HVAC system/elevator manufacturing /lighting and electrical system, total about 2000tons steelworks fabricated with one link bridge between the tower and new Venetian restaurant building, the overall height of Eiffel tower in Macao is about 338 meters and site erection work was completed by June of 2016.

   His major job was that:

   Coordinated and supervised all steel work fabrication progress/quality activities; reviewing and approve all purchase orders /monthly production plan /delivery schedule that prepared by supplier and sub-contractors for ensure compliance with the contract requirement; manage the variations from supplier/sub-contractors; control and manage all QA responsibilities ;submit weekly QA/QC report/monthly production schedule report to Hong Kong head-office; reviewed and approved all the final QC dossiers from supplier, including the production delivery list, as built drawings, SDM/NCR closed,.....etc; take some of other responsibilities on site work from the project manager.

80MW DC furnace Construction supervisor –Koniambo Nickle Plant (KNP)Project in New Caledonia

Assigned with Hatch Australia

Privately Held; 10,001+ employees; Mining & Metals industry

Jan. 2012 –  Oct. 2013

KNP Nickel Plant is located at Vavouto Koniambo massif in New Caledonia north side. It is the biggest and most important plant for New Caledonia’s economic redistribution and industry development, the design production capacity is above 60000 tons/year high pure nickel mining.

Peter was assigned in A300 smelter plant as a Construction supervisor in this project, and his major responsibility was to supervise 80MW DC furnace(total 2 units for both production lines ) overall construction work, including safety consul-ant on construction site:  

      Daily monitoring firefighting protection/explosion proof situation on construction site, inspected the electrical tools/equipments and materials and make sure to used properly around area of zone 0/zone 1/zone 2  ,Supervised the project daily tools box meeting/JSA/construction method/labor resource/material MSDS /certificates validation ; especially on confine space/equipment operation/fuel gas filling/coating/hot work/work on height/heavy lift and the areas when a flammable medium(gas/vapor/mists/dust,...etc) was present to a dangerous quantity. Used gas detection/fire and smoke detectors to check and reduce the fire accident/explosion hazard risk in time.

     Daily cooperated with the project contractor - CMIIC  for ensuring construction progress/QC management be under control of Xstrata Nickel client, daily monitoring and advised on construction safety issue,like fireproof  protection,height work , explosion equipment inspected and testing around furnace construction area;working out the mobilization plan of equipment&material&labor from CMIIC according to project workload and schedule requirement;  reviewing and approved the related lift study plan and PTW before heavy lift activities from job site; reviewing CMIIC 's  monthly/weekly construction progress.

In this period, he was closely working and supervising all the construction works which related to 80MW DC furnace installation and mechanical completion hand over works, including the activities from equipment preservation&receiving inspection & protection, heavy pieces transportation & pre-assembly work and all the furnace mechanical installation activities  on site, such as furnace sidewall /BSR/FSR/ roof panels /belly banding system/cathode bus bar/anode bus bar/  maintenance cranes/ plate coolers &cooling water pipes/refractory / hearth exhaust fans/feed pipes/electrode additional machine/ electrode arm hydraulic system/furnace transformer room HVAC system/ore feed weigh bin/coal day bin,…...etc. He has successfully completed both production lines of DC furnace construction and pre-commissioning work.  

Area 300 constcution  supervisor –Xstrata Nickle Plant Project in New Caledonia

Assigned with Hatch Australia 

Privately Held; 10,001+ employees; Mining & Metals industry

Apr. 2011 – Dec. 2011

In this period, Peter ’s major responsibility was to supervise A300 area construction safety/schedule /quality activities in KNP project,  including all the static &dynamic equipment installation & alignment and pre-commissioning work, such as the ore feed drier system/ metal calcining system /ore conveying system /safety and fireproof system…….etc.,  performed explosion hazard assessment/fire accident risk assessment on daily basis ,take action immediately to prevent and control of fires/explosions. Supervised the project daily tools box meeting/JSA/construction method/labor resource/material MSDS /certificates validation ; especially on confine space/equipment operation/fuel gas filling/coating/hot work/work on height/heavy lift and the areas when a flammable medium(gas/vapor/mists/dust,...etc) was present to a dangerous quantity. Used gas detection/fire and smoke detectors to check and reduce the fire accident/explosion hazard risk in time.

 

 

  Daily coordinated with Sarene heavy lift team/Kaffer scaffolding contractor; assisted with vendor site repre. who coming from ABB /Polysius /Siemens/SIMODA/Technip/Hatch Canada company and the third party(APARVE) to solve field equipment installation issue; supervised all construction activities related to rotating equipment including preservation inspection &protection&transportation&erection&alignment&leveling and foundation grouting works on site; daily monitoring CMIIC construction schedule / quality and safety status on site for meeting with the client design drawing &code and standards requirement; work out CMIIC mobilization plan of equipment &material and labor according to the workload and construction schedule; reviewed and approved CMIIC lift study procedure&method statement&PTW (PERMIT) and JSA plan; prepared and issued the related mechanical installation field change work (SDM and CSI) documents for ensuing field construction under control of KNS client schedule requirement.....etc.

Peter already successfully completed about 600 units dynamic /static equipments installation work, such as hammer mill, FOG fan, COG fan, baghouse fan, dynamic separator& cyclone stage1/2/3, drier ore Silo& oil pump& air compressor& bag house filter, boiler, generator, HVAC duct, air condition units, elevator and fluid bed reducer, coal day bin, weigh bin, safety and fireproof equipment,…etc.

  Fabrication superintendent– Shanghai pre-assembly yard in Nickle Plant Project 

Assigned with Hatch China ,work location: ZPMC supplier

Privately Held; 10,001+ employees; Mining & Metals industry

Sep. 2009 – Mar. 2011:

At this period, peter was assigned as a fabrication  superintendent in client which come from Canada Xstrata Nickel,  his primary responsibility was to supervise  steel structure fabrication  progress safety and quality activity management from  the project contractor -ZPMC (Zheng Hua Port Mechanical Company ) in China and sub-contractor -SCK from Japan,  the major construction work in this project was that for smelter plant steel structure fabrication & pre-assembly work ;process pipeline pre-fabrication work; and also including the equipment foundations & pipe racks& cable trays  fabrication work in A200 utility facility area; final packaging &shipment work to NC site after all pre-assembly work completed.  

He was in charge of steel structures construction management  through pre- fabrication to assembly and packaging& shipment work,  daily coordinated the field construction activities with Xstrata Nickel client from Canada and the third party from BV; supervised and coordinated with ZPMC on site for the steel structure construction schedule/technical issue /lift equipment/facilities and safety management; daily  monitored contractor field construction manpower plan; issue steel structure material PO list ; monitored and supervised ZPMC shop drawing & construction procedure& structure panel erection lift method implement at workshop, verified field construction TQ &design change work and NCR completion status, punch list works final confirm before packing and shipment,…..etc.

Peter has been successfully supervised about 23000tons steel structures workshop fabrication& assembly &packaging and shipping work; also including 1500tons’ process piping fabrication & hydro-test work and 500tons cable tray fabrication work.

 Mechanical inspection specialist

ConocoPhillips Co. in China 

Public Company; 10,001+ employees; COPC Bohai Development Project of Penglai 19-3 phase II; Oil & gas Energy industry

Aug. 2005 – Aug. 2009 (4 years) 

In this period, Peter’s major job was assigned as a mechanical inspection specialist, his primary responsibility was that:

. Assisted project QC manager to supervise the project contractor -COOEC (China Offshore Oil Engineering Company) mechanical field installation quality activities are fully developed and being implemented by regular auditing/monitoring/ surveillance activities under control in client, including equipment preservation, inspection,protection,transportation ,civil foundation checking, erection& alignment, leveling bolting &grouting works on rotating equipment and the  materials&equipments&schedule & labors management on job site.
. Assisted and cooperated with the third party( DNV) of project quality supervision Bureau for resolve construction quality issues as needed. Participate QC regular activities and associated correction actions. Promote effective and efficient operation and improvement of the quality management system.
. Established relationship and liaised with COOEC safety department to ensure project safety goals and objectives are met with client requirement.
. Participate in QA audit and procedure audit to ensure COOEC Quality assurance system(QSA) to meet with ConocoPhillips client requirements; established the relationship and liaised with COOEC quality personals to ensure field quality goals and objectives are under control of client.

. Involved project as-built documents dossier close-out and handover work and ensure the certification review was done under project requirements.  

In this project, Peter has been successfully accomplished 6 oil& gas platforms 'steel  structure fabrication and erection work- WHPC (Wellhead platform-C), WHPB, RUP /WHPD/WHPE/WHPF ,which involved  6 jackets foundation construction  & FPSO Bohai Peng Bo -117 ship SYMS yoke system and one flotation tank construction ;successfully completed these  platforms’ static &dynamic equipment installation inspection work(total 600 units, around 100 units per module), included marine crane, chemical injection skid, generator ,pumps, fireproof &safety & life save equipment, air conditions and HVAC duct through pre-assembly& erection to pre-commissioning work.....

Jan. 2003 – Jul. 2005

CSPC project ,LOP Area construction superitendent , 

Shell Company, assigned to JGC Co. Ltd.

Public Company; 10,001+ employees; CNOOC Petrochemical Nana Project (CSPC) in Huizhou city of China;   Oil and Petro-chemical industry. 

This project is China's petrochemical industry with a world-class scale, international leading technology, world-class management level, the largest joint venture project, covering 2.6 square kilometers ,a total investment of 4.3 billion, annual production capacity about 800,000 tons.JGC Company as a world PMC leader for oil, gas and petrochemical facilities, it was carried out the engineering, equipment, material procurement, construction and commissioning for the heart of the complex, Lower Olefin Plant Unit in this project.

In this project, peter was assigned as an area construction superintendent in JGC company, his major job was that in charge of  LOP (Lower Olefin Plant Unit) and cracking Furnace and Quench Oil area’s equipment field installation work; and supervised 20,000 tons’ pipe racks’ steel structure fabrication/ erection work; daily coordinated field construction schedule/safety activities .

      In this project, peter was in charge of overall project safety management at construction site, his responsibility as that:

    -Daily monitoring firefighting protection/explosion proof situation on site, inspected the electrical tools/equipments and materials and make sure to used properly around area of zone 0/zone 1/zone 2  

    --Ensuring site construction/designing/operation/maintainance activities under safety running, take the safety responsibility for overall project peoples,like Building owners,end-user,architects,consultant engineers, control company,contractor/installers,production suppliers/manufacturers...etc.  

c. Provided design consultant and reasonable suggestions to improve construction/operation condition on safety/technical/schedule /cost/quality cases.

   --  Reviewing and approval project fireproofing/explosion proof plan /emergency escape plan/workshop safety allocation map/high accident hardzards area /operation area safety route map plan.   

 

---Supervised the project daily tools box meeting/JSA/construction method/labor resource/material MSDS /certificates validation ; especially on confine space/equipment operation/fuel gas filling/coating/hot work/work on height/heavy lift and the areas when a flammable medium(gas/vapor/mists/dust,...etc) was present to a dangerous quantity. Used gas detection/fire and smoke detectors to check and reduce the fire accident/explosion hazard risk in time.

He  has successfully completed all petrochemical  equipment’ process pipe installation connection and pipe pressure test works(about 2000 meters), and about 600 units’ petrochemical equipment  lifting up and erection and final alignment work,  included the turbine generators, air Compressors, air blower skid, firewater Pumps, vertical type &horizontal type chemical reaction tower and other associated petrochemical equipment; also completed HVAC duct fabrication and installation work in cracking Furnace control room; crack furnace equipment installation and pre-commissioning test …….etc ,.

Construction supervisor/safety adviser

BP Arco Co. in Zhanjiang of China Mar. of 2000-Dec. of 2002

Public Company; 10,001+ employees;  BP/ACI Yacheng 13-1 Wet Gas Compressor   &SRP living quarter construction  Project, at Zhanjiang city of China;   Oil & gas energy industry

In this project, Peter has been in charge of WGC/SRP offshore oil/gas platform construction safety work ,his responsibility was that:

 

-- Daily monitored and advised on construction safety issue,reviewed and approval  PTW permit for  fireproof  protection,height working , confine space ,hot work control.

    -- Daily inspected the electrical tools/equipments and materials and make sure to used properly around area of zone 0/zone 1/zone 2  

B. Ensuring site construction/designing/operation/maintainance activities under safety running, take the safety responsibility for overall project peoples,like Building owners,end-user,architects,consultant engineers, control company,contractor/installers,production suppliers/manufacturers,maintainance...etc.  

-- Provided design consultant and reasonable suggestions to improve construction/operation condition on safety/technical/schedule /cost/quality cases.

--Reviewing and approval project fireproofing/explosion proof plan /emergency escape plan/workshop safety allocation map/high accident hardzards area /operation area safety route map plan.   

 

---Supervised the project daily tools box meeting/JSA/construction method/labor resource/material MSDS /certificates validation ; especially on confine space/equipment operation/fuel gas filling/coating/hot work/work on height/heavy lift and the areas when a flammable medium(gas/vapor/mists/dust,...etc) was present to a dangerous quantity. Used gas detection/fire and smoke detectors to check and reduce the fire accident/explosion hazard risk in time.

  ---Performed explosion hazard assessment/fire accident risk assessment on daily basis ,take action immediately to prevent and control of fires/explosions.

 

  ---prepared weekly/monthly safety  report and shared with project manager; and also he was in charge of whole project schedule/quality  control through fabrication to erection onshore, involved process piping, top decks , riser pipes and jackets; involved all of static& dynamic equipment through erection to alignment and per-commissioning before commissioning start up.

---Supervised mechanical field construction schedule control activities through preservation to transportation & erection&alignment and pee-commissioning work; monitored the construction schedule under control of good safety and quality condition as per BP client requirement for ensuring  whole project’s zero serious incident and zero quality defect target; reviewed and approved UOOC mechanical installation drawing& method statement and related construction procedures; worked out UOOC mobilization plan of equipment& material &labor management according to the workload and client schedule requirement ; involved UOCC daily DSTI meeting for ensuring all field construction activities under control in safety condition.

Peter has successfully accomplished that Wet Gas Compress platform(around 8000 tons weight) and one SRP Living quarter module construction supervision; this SRP Living quarter module can meet 100 men living capacity on offshore, total 6 levels  with one helideck  roof about 80 meters height,

Mechanical supervisor 

Zhanjiang Branch Co. of China Offshore Oil Engineering Company

1999-2000

Public Company; 20,001+ employees; Dongfang CEP-1 oil/gas platform construction project , at Zhanjiang base in China;   Oil &gas energy industry  

Dongfang CEP-1 platform was a Well-head oil/gas platform, was installed on south sea of China, total design weight about 6300tons.In this project, peter has worked for United Offshore Oil Branch Company of COOEC in Zhanjiang port, as a mechanical supervisor, his main responsibility was that  in charge of these 2 modules field construction and p recommissioning work, involved carrying out mechanical punch list and site instruction works for water injection HP pumps, chemical injection packages, glycerin regeneration skid,turbine generator,fire water pumps, diesel tank,gas coolers, tote tanks, sand filter package, pig launchers, vacuum pump skids ,.....etc; reviewed and approved Sub-contractor offshore oil platform fabrication drawing ,construction method statement, and related construction procedure ,daily monitored and supervised field construction activities in field,including  construction progress and safety management, materials&tools and facility management, manpower resource  management,and coordinated for the heavy lift equipment ;assisted construction superintendent to witness and report the monthly construction schedule for ensuring field construction in safety and good housekeeping condition;found out the safety potential hazards and quality defects daily by daily and supplied the effective and reasonable construction methods to fix the construction issues in time from job site;reviewed and approved the related JSA&lift study &transportation plan and method statement prior to heavy lift activities on site.

In this period, Peter has successfully completed two oil&gas platforms onshore construction work : DongFang-CEP1-1 and Suizhou36-1.

1997-1999 Mechanical Supervisor

Public Company; 5,001+ employees; China Guangzhou shipyard international Co. Ltd, Shipping Manufacture Industry.  

Peter has worked for this company as a mechanical supervisor from Norway client about 2 years and  he was in charge of  three shipbuildings’ manufacturing supervision work on safety/schedule/quality...etc, including ballasting tank & fuel oil tank& lube oil tank &bilge tank& hydraulic oil tank fabrication work and water tight test before assembly; supervised the shipbuilding hull structure construction work through pr-fabrication to assembly work in port; supervised field construction works and make sure contractor construction progress under control in safety and good quality condition ;checked and work out closely with the rotating equipment alignment work to make sure all construction activities  in compliance with design drawings, project specification and applicable codes; daily monitoring and advised on construction safety issue,like fireproof  and escape plan,,height work protection, explosion equipment inspected and testing at construction site

 He has successfully completed 3 ship buildings manufacture , such as: 4x700 TEU container and 1x17600 Ton bulk carrier new shipbuilding ; 2x70M & 4x58.7M multipurpose new shipbuilding vessels.

1995-1997   Construction superitendent

Public Company;40,001+ employees; SINOHYDRO Bureau Eighth Co., Ltd of China, Yangtze River Three Gorges Waterpower Plant Project ;Hydropower & Energy industry  

In this project,peter has supervised Yangze River Three Gorges waterpower Station plant building and more than10,000 tons steel structure radial gates construction work through fabrication to  erection and pre-commssioning work.

1993-1995 Construction supervisor 

Sino hydro Bureau Eighth Co. of China, Shenzhen Mawan Firepower station Phase-II Project 

Peter has worked in this project as a steel structure construction supervisor in Shenzhen Mawan Firepower Plant Phase II project .He has successfully completed 15000 tons’ firepower plant steel structure/equipment foundation field erection work. His major job was to supervise project sub-contractor construction activity in field of safety/schedule& labor manpower and material &tools arrangement; daily coordinated with the project client /the third party Inspection Company from BV Company to ensure compliance with project quality& specifications& standards and schedule requirement;daily monitoring and advised on construction safety issue,like fireproof  protection,height work , confine space,explosion equipment inspected and testing at construction site. 

Short description: I am interesting to joint BASSETTI team
Company name
Country
Company address: Shanghai
Slogan: Safety firstly
Telephone: 0731-57898371
Interests
Skills
Mobile phone: 18670287185
Skype username: peter.zhou70